[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1170618,834,1,"单选题","分部工程应由（）组织施工单位项目负责人和技术、质量负责人等进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",true,{"key":16,"text":17,"correct":18},"B","总监理工程师代表",false,{"key":20,"text":21,"correct":18},"C","专业监理工程师",{"key":23,"text":24,"correct":18},"D","监理工程师","分部工程应由总监理工程师（建设单位项目负责人）组织施工单位项目负责人和技术、质量负责人等进行验收",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]