[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1170582,834,1,"单选题","甲中学拟在校园内建造一幢四层教学楼，通过招投标选择乙设计院进行建筑设计、丙监理公司进行工程监理、丁建筑公司进行建筑施工。教学楼建主体结构采用钢筋混凝土框架结构、柱下钢筋混凝土井格基础，建筑面积为2000㎡。 在工程准备阶段收集了以下工程资料：①建设工程施工许可证；②建设工程规划许可证；③可行性研究报告；④建设用地规划许可证；⑤项目建议书等。工程文件资料产生先后次序排列正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","⑤④③②①",false,{"key":16,"text":17,"correct":18},"B","⑤③④②①",true,{"key":20,"text":21,"correct":14},"C","⑤④③①②",{"key":23,"text":24,"correct":14},"D","③②⑤④①","在工程准备阶段收集了以下工程资料：项目建议书等；可行性研究报告；建设用地规划许可证；建设工程规划许可证；设工程施工许可证；",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]