[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170558":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1170558,834,1,"单选题","单位工程完工后应由（）单位组织验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设",true,{"key":16,"text":17,"correct":18},"B","监理",false,{"key":20,"text":21,"correct":18},"C","设计",{"key":23,"text":24,"correct":18},"D","施工","建设单位收到工程验收报告后，应由建设单位（项目）负责人组织施工（含分包单位）、设计、监理等单位（项目）负责人进行单位工程（子单位）工程验收。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]