[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170553":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1170553,834,1,"单选题","分部工程质量验收由（）组织。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",true,{"key":16,"text":17,"correct":18},"B","监理工程师",false,{"key":20,"text":21,"correct":18},"C","施工单位项目技术负责人",{"key":23,"text":24,"correct":18},"D","质检员","本题考查的是分部工程质量验收。分部（子分部）工程质量验收应由总监理工程师组织施工单位项目负责人和项目技术、质量负责人等进行。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]