[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1170407,834,1,"单选题","某建筑公司甲项目部承建某学校办公楼的施工任务。该办公楼为六层钢筋混凝土框架结构、柱下条型基础，建筑面积为10000㎡.工程于2001年7月20日开工，至2012年12月20日完工并通过了竣工验收。 甲项目部资料员对施工文件资料进行整理、立卷和归档的时间是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程竣工验收前",true,{"key":16,"text":17,"correct":18},"B","工程竣工验收后",false,{"key":20,"text":21,"correct":18},"C","竣工备案前",{"key":23,"text":24,"correct":18},"D","竣工备案后","项目部资料员对施工文件资料进行整理、立卷和归档的时间是工程竣工验收前。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]