[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170362":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1170362,834,1,"单选题","由专业承包单位施工的分部（分项）工程或专项工程的施工方案，应由（）审批。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总包单位技术负责人",false,{"key":16,"text":17,"correct":14},"B","总包单位项目技术负责",{"key":19,"text":20,"correct":21},"C","专业承包单位技术负责人",true,{"key":23,"text":24,"correct":14},"D","专业承包单位项目技术负责人","专业承包单位施工的分部（分项）工程或专项工程的施工方案，应由专业承包单位技术负责人审批。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]