[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1170355,834,1,"单选题","分部工程验收结论由（）填写。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",true,{"key":16,"text":17,"correct":18},"B","专业监理工程师",false,{"key":20,"text":21,"correct":18},"C","总监理工程师代表",{"key":23,"text":24,"correct":18},"D","监理工程师","分部工程由总监理工程师组织施工项目经理及有关勘察（地基与基础部分）、设计（地基与基础及主体结构）单位项目负责人进行验收，并按分部（子部分）工程验收记录表的要求进行记录。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]