[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170306":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1170306,834,1,"单选题","在下列施工技术资料中仅需要施工单位过程保存的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程洽商记录",false,{"key":16,"text":17,"correct":18},"B","设计变更通知单",true,{"key":20,"text":21,"correct":14},"C","图纸会审记录",{"key":23,"text":24,"correct":14},"D","技术交底记录","设计变更通知单在施工技术资料中仅需要施工单位过程保存。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]