[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1170288,834,1,"单选题","分项工程质量验收程序及资料管理流程有①检验批施工完成②自检③下道工序④验收（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③④",false,{"key":16,"text":17,"correct":18},"B","①②④③",true,{"key":20,"text":21,"correct":14},"C","①③②④",{"key":23,"text":24,"correct":14},"D","③①②④","分项工程质量验收程序及资料管理流程如图8-4所示，管理流程为检验批施工完成、自检、验收、下道工序。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]