[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1170275,834,1,"单选题","计划编制时，（）按分类规定属于施工单位物资文件。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工检测计划",false,{"key":16,"text":17,"correct":14},"B","施工组织设计及施工方案",{"key":19,"text":20,"correct":21},"C","材料检测报告",true,{"key":23,"text":24,"correct":14},"D","工程定位测量记录","计划编制时，材料检测报告按分类规定属于施工单位物资文件。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]