[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170269":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1170269,834,1,"单选题","计划编制时，（）按分类规定属于施工单位技术文件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量保证书",false,{"key":16,"text":17,"correct":18},"B","施工组织设计及施工方案",true,{"key":20,"text":21,"correct":14},"C","材料检测报告",{"key":23,"text":24,"correct":14},"D","工程定位测量记录","计划编制时，施工组织设计及施工方案按分类规定属于施工单位技术文件。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]