[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170252":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1170252,834,1,"单选题","单位（子单位）工程质量验收程序及资料管理流程有①分部（子分部）施工完成②预验收③工程移交④验收（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①②③④",false,{"key":16,"text":17,"correct":14},"B","②④①③",{"key":19,"text":20,"correct":21},"C","①②④③",true,{"key":23,"text":24,"correct":14},"D","③①②④","单位（子单位）工程质量验收程序及资料管理流程如图8-6所示，管理流程为分部（子分部）施工完成、预验收、验收、工程移交。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]