[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170243":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1170243,834,1,"单选题","分项工程检查结论由（）填写。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单位（项目）负责人",false,{"key":16,"text":17,"correct":14},"B","项目经理",{"key":19,"text":20,"correct":14},"C","项目专业质量员",{"key":22,"text":23,"correct":24},"D","项目专业技术负责人",true,"表分项工程质量验收记录中检查结论中签字人员是项目专业技术负责人。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]