[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170206":3},{"question":4,"library":22},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":21},1170206,834,1,"单选题","工程实施阶段施工单位应形成（）类文件。",[11,14,16,19],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D","工程实施阶段施工单位应形成C类文件。",{"id":6,"name":23,"category":24,"favorite":25},"(资料员)专业管理实务 岗位知识","建筑工程",0]