[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1170144,834,1,"单选题","单位工程质量验收合格（）日内应将有关资料报建设行政主管部门备案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","15",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","30","建设单位应在单位工程竣工验收合格15日内将《建设工程竣工验收报告》和有关文件，报建设工程备案机关办理竣工工程验收备案手续。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]