[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170136":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1170136,834,1,"单选题","建筑工程竣工验收备案的基础工作应是通过竣工验收，完成（）文件收集整理，准备提交备案文件。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工文件",false,{"key":16,"text":17,"correct":14},"B","监理文件",{"key":19,"text":20,"correct":21},"C","竣工验收文件",true,{"key":23,"text":24,"correct":14},"D","归档文件","建筑工程竣工验收备案的基础工作应是通过竣工验收，完成竣工验收文件文件收集整理，准备提交备案文件。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)专业管理实务 岗位知识","建筑工程",0]