[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170090":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1170090,833,3,"判断题","工程施工分包是指承包人将中标工程项目分解后分别发包给具有相应资质的企业完成。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"转包是指承包单位承包建设工程后，不履行合同约定的责任和义务，将其承包的全部建设工程转给他人或者将其承包的全部建设工程肢解以后以分包的名义分别转给其他单位承包的行为。",{"id":6,"name":21,"category":22,"favorite":23},"(资料员)基础知识","建筑工程",0]