[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169977":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1169977,833,3,"判断题","发包人供应材料与工程设备，承包人应提前20天通过监理人以书面形式通知发包人供应材料与工程设备进场。（）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"发包人供应材料与工程设备，承包人应提前30天通过监理人以书面形式通知发包人供应材料与工程设备进场。",{"id":6,"name":21,"category":22,"favorite":23},"(资料员)基础知识","建筑工程",0]