[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169964":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1169964,833,3,"判断题","采用工程量清单方式招标，工程量清单必须作为招标文件的组成部分，其准确性和完整性由投标人负责。（）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"采用工程量清单方式招标，工程量清单必须作为招标文件的组成部分，其准确性和完整性由招标人负责。",{"id":6,"name":21,"category":22,"favorite":23},"(资料员)基础知识","建筑工程",0]