[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169943":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1169943,833,3,"判断题","分包工程价格的高低，不会对项目经理部的施工项目成本产生一定的影响。（）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"分包工程价格的高低，必然对项目经理部的施工项目成本产生一定的影响。",{"id":6,"name":21,"category":22,"favorite":23},"(资料员)基础知识","建筑工程",0]