[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169929":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1169929,833,3,"判断题","施工项目成本核算的对象按单位工程划分，以一个季度为一个核算期，采用会计核算、统计核算、业务核算“三算结合”的方法。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"施工项目成本核算的对象按单位工程划分，以一个月为一个核算期，采用会计核算、统计核算、业务核算“三算结合”的方法。",{"id":6,"name":21,"category":22,"favorite":23},"(资料员)基础知识","建筑工程",0]