[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169927":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1169927,833,3,"判断题","建立工程进度报告制度及信息沟通网络属于进度控制措施的管理措施。（）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"进度控制的措施主要包括组织措施、管理措施、经济措施和技术措施。1.组织措施。1）建立进度控制目标体系。2)建立工程进度报告制度及信息沟通网络。",{"id":6,"name":21,"category":22,"favorite":23},"(资料员)基础知识","建筑工程",0]