[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169886":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1169886,833,3,"判断题","混凝土拌合料运到浇筑地点时应具有设计配合比所规定的坍落度。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"混凝土拌合料自商品混凝土厂装车后，应及时运至浇筑地点。混凝土拌合料运输过程中一般要求：保持其均匀性，不离析、不漏浆；运到浇筑地点时应具有设计配合比所规定的坍落度；应在混凝土初凝前浇入模板并捣实完毕；保证混凝土能浇筑连续进行。",{"id":6,"name":21,"category":22,"favorite":23},"(资料员)基础知识","建筑工程",0]