[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169656":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1169656,833,2,"多选题","以下各项中不属于施工资源管理的任务的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","规划及报批施工用地",true,{"key":16,"text":17,"correct":18},"B","确定资源类型及数量",false,{"key":20,"text":21,"correct":18},"C","确定资源的分配计划",{"key":23,"text":24,"correct":14},"D","建立施工现场管理组织",{"key":26,"text":27,"correct":18},"E","施工资源进度计划的执行和动态调整","AD","施工资源管理的任务：确定资源类型及数量；确定资源的分配计划；编制资源进度计划；施工资源进度计划的执行和动态调整。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)基础知识","建筑工程",0]