[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169653":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1169653,833,2,"多选题","施工成本控制的依据包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","市场价",false,{"key":16,"text":17,"correct":18},"B","工程变更",true,{"key":20,"text":21,"correct":18},"C","进度报告",{"key":23,"text":24,"correct":18},"D","施工成本计划",{"key":26,"text":27,"correct":18},"E","承包合同","BCDE","施工成本控制的依据包括以下内容。(1)工程承包合同(2)施工成本计划(3)进度报告(4)工程变更除了上述几种施工成本控制工作的主要依据以外，有关施工组织设计、分包合同文本等也都是施工成本控制的依据。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)基础知识","建筑工程",0]