[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169636":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1169636,833,2,"多选题","施工项目目标控制的任务包括（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","进度控制",true,{"key":16,"text":17,"correct":14},"B","质量控制",{"key":19,"text":20,"correct":14},"C","成本控制",{"key":22,"text":23,"correct":24},"D","材料消耗控制",false,{"key":26,"text":27,"correct":24},"E","盈利目标控制","ABC","施工项目控制的任务是进行以项目进度控制、质量控制、成本控制和安全控制为主要内容的四大控制。其中前三项目标是施工项目成果，而安全目标是指施工过程中人和物的状态。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)基础知识","建筑工程",0]