[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169633":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1169633,833,2,"多选题","下列可作为施工成本控制依据的是（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包合同",true,{"key":16,"text":17,"correct":18},"B","施工方法",false,{"key":20,"text":21,"correct":14},"C","进度报告",{"key":23,"text":24,"correct":14},"D","工程变更",{"key":26,"text":27,"correct":14},"E","成本计划","ACDE","施工成本控制的侬据工程承包合同。施工成本计划。进度报告。工程变更。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)基础知识","建筑工程",0]