[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169630":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1169630,833,2,"多选题","消除或减少焊接残余变形和残余应力的施工措施主要有（）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","采用合理的施焊次序",true,{"key":16,"text":17,"correct":14},"B","施焊前给构件一个和残余变形相反的预变形",{"key":19,"text":20,"correct":21},"C","对于小尺寸焊件，在施焊后急冷",false,{"key":23,"text":24,"correct":14},"D","采用机械校正法消除焊接残余变形",{"key":26,"text":27,"correct":14},"E","对于小尺寸焊件，在施焊前预热","ABDE","消除或减少焊接残余变形和残余应力的施工措施:1)采用合理的施焊次序，如分段退焊、分层焊、对角跳焊等。2)施焊前给构件一个和焊接变形相反的预变形，使构件在焊接后产生的焊接变形与之抵消。3)对于小尺寸焊件，在施焊前预热，或施焊后回火。4)采用机械校正法消除焊接残余变形。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)基础知识","建筑工程",0]