[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169455":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1169455,833,1,"单选题","下列关于时间定额和产量定额的说法中正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时间定额和产量定额互为倒数",true,{"key":16,"text":17,"correct":18},"B","时间定额和产量定额都是材料定额的表现形式",false,{"key":20,"text":21,"correct":18},"C","施工定额可以用时间定额来表示",{"key":23,"text":24,"correct":18},"D","劳动定额的表现形式是产量定额","时间定额用工人完成单位的工程量需要消耗的时间来表示劳动消耗，而产量定额用工人在单位时间内能够完成的工程数量来表示劳动消耗。因此时间定额与产量定额应该互为倒数。时间定额与产量定额是劳动定额两种重要的表现形式。两者之间的关系也为编制定额提供了方法。机械台班定额在表现形式上与人工定额相一致，也是经常考核的内容。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]