[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1169287,833,1,"单选题","因分部分项工程量清单漏项或非承包人的原因的工程变更，造成增加新的工程量清单项目，下列对应的综合单价确定方法错误的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同中已有适用的综合单价，按合同中已有的综合单价确定",false,{"key":16,"text":17,"correct":14},"B","合同中有类似的综合单价，参照类似的综合单价确定",{"key":19,"text":20,"correct":21},"C","合同中没有适用或类似的综合单价，由监理工程师提出综合单价，经发包人确认后执行",true,{"key":23,"text":24,"correct":14},"D","合同中没有适用或类似的综合单价，由承包人提出综合单价，经发包人确认后执行","约定的因非承包商原因导致的工程变更，对应的综合单价按下列方法确定：(1)合同中已有适用的综合单价，按合同中已有的综合单价确定；(2)合同中有类似的综合单价，参照类似的综合单价确定；(3)合同中没有适用或类似的综合单价，由承包人提出综合单价，经发包人确认后执行。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]