[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169286":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1169286,833,1,"单选题","工程量清单的编制依据不包括（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设工程文件",false,{"key":16,"text":17,"correct":14},"B","地质勘察报告",{"key":19,"text":20,"correct":14},"C","计价规范",{"key":22,"text":23,"correct":24},"D","标准、规范、技术资料",true,"编制工程量清单的依据《建设工程工程量清单计价规范》(2)国家或省级、行业建设主管部门颁发的计价依据和办法。(3)建设工程设计文件及相关资料。(4)与建设工程有关的标准、规范、技术资料。(5)拟定的招标文件。(6)施工现场情况、地勘水文资料、工程特点及常规施工方案。(7)其他相关资料。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]