[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169254":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1169254,833,1,"单选题","大型机械设备进出场及安拆费属于（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程费",false,{"key":16,"text":17,"correct":18},"B","措施项目费",true,{"key":20,"text":21,"correct":14},"C","其他项目费",{"key":23,"text":24,"correct":14},"D","规费","措施费是指为完成工程项目施工，发生于该工程施工前和施工过程中非工程实体项目的费用。包括内环境保护费、文明施工费、安全施工费、临时设施费、夜间施工费、二次搬运费、大型机械设备进出场及安拆费、混凝土、钢筋混凝土模板及支架费、脚手架费、已完工程及设备保护费、施工排水、降水费。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]