[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169200":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1169200,833,1,"单选题","竣工决算的编制单位是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","施工单位",false,{"key":20,"text":21,"correct":18},"C","设计单位",{"key":23,"text":24,"correct":18},"D","监理单位","竣工验收阶段的造价计算是工程结算和竣工决算。工程结算是施工企业按照合同约定全部完成所承包的工程，经验收质量合格，并符合合同要求后向发包单位提交的最终工程结算文件。工程结算是一种动态的工程造价计算，是按照工程实际发生的量与价来计算的，经审查通过的工程结算是核定建设工程造价的依据。竣工决算是建设项目验收合格交付使用后↓由建设单位编制的反映.工程项目实际造价和投资效果的文件，竣工决算包括建设工程项目从决策阶段到竣工交付使用全过程的全部费用，其内容有建筑工程费、安装工程费、设备工器具购置费、工程建设其他费、预备费等。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]