[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169185":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1169185,833,1,"单选题","出现下列（）情况时，在工程计量时不能按承包人实际完成的工程量计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量清单漏项",false,{"key":16,"text":17,"correct":18},"B","天气原因造成工程量的增加",true,{"key":20,"text":21,"correct":14},"C","工程量清单中工程量计算错误",{"key":23,"text":24,"correct":14},"D","工程变更引起工程量增减","当出现天气原因造成工程量的增加情况时，在工程计量时不能按承包人实际完成的工程量计算。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]