[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169161":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1169161,833,1,"单选题","其他项目清单是指分部分项工程量清单、措施项目清单所包含的内容以外，因招标人的特殊要求而发生的与拟建工程有关的其他费用项目和相应数量的清单，一般不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总承包服务费",false,{"key":16,"text":17,"correct":18},"B","规费",true,{"key":20,"text":21,"correct":14},"C","计日工",{"key":23,"text":24,"correct":14},"D","暂列金额和暂估价","其他项目清单的编制：暂列金额。暂估价，包括材料暂估单价、工程设备暂估单价、专业工程暂估价。计日工。总承包服务费。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]