[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1169148,833,1,"单选题","供暖系统的相关材料进场时应经（）认可，同时形成相应的验收记录。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","资料员",{"key":19,"text":20,"correct":21},"C","监理工程师",true,{"key":23,"text":24,"correct":14},"D","技术负责人","供暖系统节能工程采用的散热设备、阀门、仪表、管材、保温材料等产品进场时，应按设计要求对其类型、材质、规格及外观等进行验收，并应由监理工程师（建设单位代表）检查认可，且应形成相对应的验收记录。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]