[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169104":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1169104,833,1,"单选题","在某工程施工过程中，通过各种因素分析，发现机械费用存在潜在问题，项目经理部及时调整了施工方案，这体现的是施工项目成本的（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","过程控制",false,{"key":16,"text":17,"correct":18},"B","事前控制",true,{"key":20,"text":21,"correct":14},"C","动态控制",{"key":23,"text":24,"correct":14},"D","全面控制","本题考查的是施工成本管理的任务。施工成本控制可分为事先控制、事中控制和事后控制。施工过程中，通过各种因素的分析，发现潜在问题，及时调整方案，这是施工成本控制中的事前控制。因是在偏差发生之前发现可能的潜在问题，并通过采取措施防止了偏差的发生，这体现的是事前控制。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]