[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169082":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1169082,833,1,"单选题","下列选项中，不属于施工项目目标控制问题的要素的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工项目",false,{"key":16,"text":17,"correct":14},"B","控制主体",{"key":19,"text":20,"correct":14},"C","纠偏措施",{"key":22,"text":23,"correct":24},"D","排除干扰",true,"施工项目目标控制问题的要素包括：施工项目、控制目标、控制主体、实施计划、实施信息、偏差数据、纠偏措施、纠偏行为。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]