[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1169069":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1169069,833,1,"单选题","高强度螺栓施工时，对每一个连接接头，应先用临时螺栓和冲钉定位，临时螺栓和冲钉的数量应由计算确定，但不少于安装孔的（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2\u002F3",false,{"key":16,"text":17,"correct":14},"B","1\u002F2",{"key":19,"text":20,"correct":21},"C","1\u002F3",true,{"key":23,"text":24,"correct":14},"D","1\u002F4","高强度螺栓施工时，对每一个连接接头，应先用临时螺栓和冲钉定位，临时螺栓和冲钉的数量应由计算确定，但不少于安装孔的1\u002F3。",{"id":6,"name":27,"category":28,"favorite":29},"(资料员)基础知识","建筑工程",0]