[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168728":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168728,832,2,"多选题","下列关于施工项目目标控制的措施说法错误的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建立完善的工程统计管理体系和统计制度属于信息管理措施",false,{"key":16,"text":17,"correct":18},"B","主要有组织措施、技术措施、合同措施、经济措施和管理措施",true,{"key":20,"text":21,"correct":14},"C","落实施工方案,在发生问题时,能适时调整工作之间的逻辑关系,加快实施进度属于技术措施",{"key":23,"text":24,"correct":18},"D","签订并实施关于工期和进度的经济承包责任制属于合同措施",{"key":26,"text":27,"correct":14},"E","落实各级进度控制的人员及其具体任务和工作责任属于组织措施","BD","",{"id":6,"name":31,"category":32,"favorite":33},"通用基础","建筑工程",0]