[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168720":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168720,832,2,"多选题","建设工程施工合同具有下列情形之一的,认定无效:( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工总承包单位将劳务作业分包给具有相应资质等级的劳务分包企业的",false,{"key":16,"text":17,"correct":18},"B","建设工程必须进行招标而未进行招标或者中标无效的",true,{"key":20,"text":21,"correct":18},"C","承包人未取得建筑施工企业资质或者超越资质等级的",{"key":23,"text":24,"correct":18},"D","没有资质的实际施工人借用有资质的建筑施工企业名义的",{"key":26,"text":27,"correct":14},"E","特级房屋建筑工程施工总承包单位承担单项建安合同额超过企业注册资本金5倍的建筑面积20万m2以上的住宅小区建设的","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"通用基础","建筑工程",0]