[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168647":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":28},1168647,832,1,"单选题","在竣工交付验收签字之日起( )日内,项目经理部要向企业工程管理部写出",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","经理部解体申请报告,同时提出善后留用和遣散人员的名单及时间,经有关部门审核批准后执行。",false,{"key":16,"text":17,"correct":18},"B","7",true,{"key":20,"text":21,"correct":14},"C","15",{"key":23,"text":24,"correct":14},"D","21",{"key":26,"text":27,"correct":14},"E","30","",{"id":6,"name":30,"category":31,"favorite":32},"通用基础","建筑工程",0]