[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168468":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1168468,832,1,"单选题","下列关于基坑（槽）开挖施工工艺的说法中,正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采用机械开挖基坑时,为避免破坏基底土,应在标高以上预留15～50cm的土层由人工挖掘修整",false,{"key":16,"text":17,"correct":18},"B","在基坑（槽）四侧或两侧挖好临时排水沟和集水井,或采用井点降水,将水位降低至坑、槽底以下500mm,以利于土方开挖",true,{"key":20,"text":21,"correct":14},"C","雨期施工时,基坑（槽）需全段开挖,尽快完成",{"key":23,"text":24,"correct":14},"D","当基坑挖好后不能立即进行下道工序时,应预留30cm的土不挖,待下道工序开始再挖至设计标高","",{"id":6,"name":27,"category":28,"favorite":29},"通用基础","建筑工程",0]