[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168402":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1168402,830,3,"判断题","发包人、承包人应当在每月20日前对上月完成劳务作业量及应支付劳务分包合同价款予以书面确认，书面确认时限自发包人收到承包人报送的书面资料之日起计算，最长不得超过3日。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"发包人、承包人应当在每月20日前对上月完成劳务作业量及应支付劳务分包合同价款予以书面确认，书面确认时限自发包人收到承包人报送的书面资料之日起计算，最长不得超过3日；发包人应当在书面确认后5日内支付已经确定的劳务分包价款。",{"id":6,"name":21,"category":22,"favorite":23},"(劳务员)专业管理实务 岗位知识","建筑工程",0]