[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168261":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1168261,830,3,"判断题","进场工种、人数一览表的格式是固定的不能更改。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"劳务员根据公司所批复的项目进度计划和劳动力使用计划编制进场工种、人数一览表，各项目部可根据本项目的自身情况进行改动。",{"id":6,"name":21,"category":22,"favorite":23},"(劳务员)专业管理实务 岗位知识","建筑工程",0]