[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168128":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168128,830,2,"多选题","根据劳务分包合同价款结算、支付的要求，应按月对劳务费进行签认，填写（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","劳务费结算支付情况月报表",true,{"key":16,"text":17,"correct":18},"B","劳务费结算支付情况季度报表",false,{"key":20,"text":21,"correct":14},"C","工程项目劳务费结算支付情况月报表",{"key":23,"text":24,"correct":18},"D","工程项目劳务费结算支付情况季度报表",{"key":26,"text":27,"correct":14},"E","劳务费结算支付情况汇总表","ACE","根据劳务分包合同价款结算、支付的要求，应按月对劳务费进行签认，填写劳务费结算支付情况汇总表、劳务费结算支付情况月报表、工程项目劳务费结算支付情况月报表。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]