[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168089":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168089,830,2,"多选题","承包商与材料供应商之间的争议，主要有以下方面（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","货物质量",true,{"key":16,"text":17,"correct":14},"B","货物数量",{"key":19,"text":20,"correct":21},"C","货物体积",false,{"key":23,"text":24,"correct":14},"D","交货期",{"key":26,"text":27,"correct":14},"E","货款","ABDE","承包人与材料设备供应商的争议，多数是货品质量、数量、交货期和付款方面的争议。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]