[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168057":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168057,830,2,"多选题","发包人有下列（ ）情形，工程所在地建设行政主管部门可以限制其承揽新的工程或者新的劳务作业。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","转包劳务作业的",true,{"key":16,"text":17,"correct":18},"B","发包人、承包人未依法订立书面劳动合同的",false,{"key":20,"text":21,"correct":14},"C","因拖欠劳务分包合同价款或者劳务作业人员工资而引发群体性事件的",{"key":23,"text":24,"correct":18},"D","发包人、承包人在未签订书面劳务分包合同并备案的情况下进场施工的",{"key":26,"text":27,"correct":18},"E","发包人、承包人不按照相关规定进行劳务作业验收和劳务分包合同价款结算的","AC","发包人或者承包人有下列情形之一的，工程所在地建设行政主管部门可以限制其承揽新的工程或者新的劳务作业：转包劳务作业的；因拖欠劳务分包合同价款或者劳务作业人员工资而引发群体性事件的；发包人、承包人有以上所列情形三次以上的。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]