[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168042":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168042,830,2,"多选题","在评价劳务分包方的施工与资源保障能力时，应重点考察（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","报价水平",false,{"key":16,"text":17,"correct":18},"B","履约能力",true,{"key":20,"text":21,"correct":14},"C","安全等级",{"key":23,"text":24,"correct":18},"D","经营行为",{"key":26,"text":27,"correct":18},"E","社会信用","BDE","在劳务分包方施工与资源保障能力评价时，应重点考察申报企业的履约能力和意愿，即企业经营、管理、财务能力状况和经营行为及社会信用。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]