[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168020":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168020,830,2,"多选题","符合劳动力需求计划的编制要求的是：（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","要保持劳动力均衡使用",true,{"key":16,"text":17,"correct":14},"B","根据工程的实物量和定额标准分析劳动需用总工日",{"key":19,"text":20,"correct":14},"C","根据施工组织设计和进度计划确定各个阶段的生产工人的数量和及各工种人员之间的比例",{"key":22,"text":23,"correct":24},"D","对工程量进行估算",false,{"key":26,"text":27,"correct":14},"E","要准确计算工程量","ABCE","3、1.1.4劳动力需求计划的编制要求：1.要保持劳动力均衡使用;2.编制依据根据工程的实物量和定额标准分析劳动需用总工日，根据施工组织设计和进度计划确定各个阶段的生产工人的数量和及各工种人员之间的比例;3.要准确计算工程量",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]